Items required for Demolition Permit Applicants
- 90 Day Demolition Delay Form with LUCR
Note* Possible enforcement of Ninety (90) Day Demolition - Copy of current license and insurance certificate
- (General Liability, Vehicles and Workman’s comp -Name City of Bridgeport as Additional insured)
- Release Form - signed and notarized.
- Hold Harmless- Declaration letter on company letter head, signed by officer of the company.
- Proof of letters to abutting/adjoining property owners (Certified Mail receipts and a sample of the letter sent)
- Fire hydrant permit from Fire Department for dust control, or a letter on Company letter head stating how dust will be controlled.
- Letter from all utility
Phone: 203-383-6679
Cable: 203-696-4726
Electric: 800-722-5584
Gas: 203-795-7792
WPCA: 203-332-5550
Water: 203-362-3062 or Demolitions@aquariumwater.com
- Dumping location and verification of acceptance of demolition debris (Letter from dump location)
- Copy of contract- fully executed between contractor and property owner.
- Public Work street opening permit or permit application signed by Public Works - City Hall Lyon Terrace Room 223, 203-576-7123
- Provide correct building address, size of building, number of stories and use of the building.
- Number of units of the building is a dwelling
- Rodent Free Certificate from Health Department (999 Broad St) 203-576-7680 (Valid for 30 days from date of issuance.)